Min-Max Planning
Min-Max Planning determines the size and timing of item
replenishment orders and creates a purchase order/move order to replenish item
stock. The PO/Move order is created based upon the Min-Max Planning Report. Min-Max Planning can be done at either
Organization Level or Sub Inventory Level
At Organization level, minimum quantity will be calculated
by summing the on hand availability of all sub inventories where as at Sub
Inventory level, minimum quantity will be checked in individual sub
inventories
We will see all these setups in detail
Start with creating an item in item master
Navigate to Items > Master Items
Give details as shown below
Give a List Price. A List Price just provides a rough idea
about the price of an item
From the above shown form, following can be concluded
1.) Maximum
1000 items can be present
2.) Minimum
of 100 items needs to be present in inventory
3.) If
there are no items in an inventory then a single requisition order with 2 lines
each of 400 will be raised
4.) If On
hand availability is 80 then order will be raised for only 920
Min-Max Planning at
Organization Level
Navigate to Planning > Min-Max Planning
Give Planning Level as Organization
Also set Restock value to Yes
If we give this option as No then only a report will be
created but interface tables won’t be hit.
Submit the concurrent program, once it completes
successfully, Min-Max Planning report will be generated
Now we need to Run Requisition Import program from
Purchasing Responsibility. But we need to cross check few points if we want
Requisition Import program to complete successfully
1.) At
Item level, list price should be set up
2.) At
Item level, in purchasing tab, expense account should be provided
3.) In
General Planning Tab, Source type must be supplier
4.) A
Location should be assigned to Inventory Organization
5.) An
Employee must be assigned to the login id
6.) Master
Organization should be associated with financial options
In case the Requisition import program ends in error
then you can run Requisition Import Exception Report Concurrent program with
Delete Exception Parameter as Yes
This program will show you the error
Except last two points, we have ensured that all conditions
are met with. We will first close last two points
Assigning employee to
the login id
Navigate to Sys Admin > Security > User > Define
Assign an employee as shown below
Associating Master
Organization with financial options
Navigate to Purchasing Super User > Setup >
Organizations > Financial Options > Supplier – Purchasing
Give the name of your Master Organization
Now run the Requisition Import Concurrent
Program from Purchasing Responsibility
This will trigger couple of other concurrent
programs as well
In order to check the requisition lines Navigate to
Purchasing Super User > Requisitions > Requisition Summary
Give Item Name & you can see that 2 lines are created
Min-Max Planning at
Sub Inventory Level
Navigate to Setup > Organizations > Subinventories
Click on Item / Subinventory Tab
Similarly give for 2nd sub inventory
Now Navigate to Planning > Min-Max Planning
Give Parameters as shown below
Keep the Sub Inventory field as null so that report will run
for all sub inventories in a particular organization
Once the request completes normally. Navigate to
Purchasing Responsibility & run requisition Import Program
Once all the concurrent requests completes successfully,
navigate to Purchasing Super User > Requisitions > Requisition Summary
This is how Min-Max Planning work. We’ll take up approvals
& creating Pos from these requisitions separately.
Good Job, Vipul
ReplyDeleteHi Vipul.. while submitting Requisition Import report i can table to See INV in source parameters. What setups i need to change. please reply to my mail. pardhasp7@gmail.com
ReplyDeleteExcellent Post Sir
ReplyDeleteNice post.
ReplyDeleteExcellent post. Sequential steps with screen shots clarify the min-max planning in eBS quite clearly.
ReplyDeleteMy min max planning report is not showing anything, what to do?
ReplyDelete