Kanban Planning Methods:
Kanban Planning is mainly used in places where an item has
to be configured by procuring raw goods from various sources
Create an item in Item Master. Navigate to Items > Master
Item
Give details as shown below
Now Navigate to Kanban > Pull Sequences > New
Give details as shown below
Card is nothing but a container. In this example, we have
defined card value as 2 which means that there are 2 containers & each will
have 100 items in it.
Add 1 more row as shown below
Now we need to generate cards, cards can be either auto
generated or else we need to generate them manually. For first row, we’ll
generate card automatically & for 2nd, we’ll do it manually
Select first row & click on Generate Cards Tab
Click Yes
Once the cards are generated, click on Cards tab to see the
cards sequence
Here supply status is New
Now we need to generate cards for other line so close this
form & select 2nd line & click on Cards
Give number manually as shown below
& save the record
Here also Supply status is New
Now close this form & go back to first line & click
on Cards. Here we need to replenish the items, so click on Replenish. With this
the requisition interface tables will be populated
We can see now that Supply status has changed to Empty
With this, we are done with Inventory Responsibility
Now navigate to purchasing responsibility & run the
requisition import program
Once this program completes successfully, you
can see the following output
In order to check the requisitions created, Navigate to
Requisitions > Requisitions Summary
Creating Purchase Orders
In order to create PO ,
navigate to Purchase Orders > AutoCreate
Give the requisition number & click on find
Now click on Automatic
A form will open, give supplier name & click on Create
With this a PO will be
created
Click on Approve to approve it
Click on OK
Now go back to Inventory Responsibility & check
the status of Card. Navigate to Inventory Super User > Kanban > Kanban
Cards
We can see that for Card Number 9493, Supply Status is In
Process
Once the goods arrive, we need to receive goods in our Sub
inventory.
Navigate to Purchasing Responsibility > Receiving >
Receipts
Search by PO Number
Save the record
Now check the Supply Status. Navigate to Inventory
Responsibility > Kanban > Kanban Cards
The card status is now full
With this, the goods are in Sub inventory 1. Now our staging
sub inventory needs these goods.
Navigate to Inventory Responsibility > Kanban > Pull
Sequences
Click on Cards
Click on Replenish
Once you click on Replenish, the card status will change to
Empty
This means that a new move order is created
Navigate to Move Orders > Move Orders
We can see that a Move order is created & Move order
type is Replenishment
Now navigate to Move Order > Transact Move Order &
give the move order number & click on find
Check the check box & click on Allocate
& then click on Transact
Once items are transacted, you can see that the Supply
status of Card 1 is Full where as that of
9493 changed back to Empty
Excellent document
ReplyDeleteThis comment has been removed by the author.
ReplyDeleteyou are mention that the move order is generated but when i replenish my card my card is empty but no move order is generated so plz help me out of this....
ReplyDelete